Summary
The $3.6 million project replacing rotted-out culverts under the Ormond shopping center is about 35% done, with businesses staying open during construction and full closeout expected in mid-2027.
At a glance
- Total mentions
- 2
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 26, 2026.
Impact analysis
The project is a roughly $3.6 million parish investment.
Ormond-area businesses and shoppers who get more reliable drainage and safer access.
Mentions & discussions (2)
Parish Council 6:00 PM - Regular Meeting / Budget Hearing (trimmed) - Oct 26, 2026
The $3.6 million project replacing rotted-out culverts under the Ormond shopping center is about 35% done, with businesses staying open during construction and full closeout expected in mid-2027.
Parish Council Meeting 6:00 PM (trimmed) - Jan 12, 2026
A $3.1 million contract finally moves forward to fix drainage in the Ormond area, which has been a bottleneck in the parish watershed for years. Council members expect construction to start within about a month and warn it will be messy while underway.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for St. Charles Parish
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.