St. Charles Parish

Summary

The $3.6 million project replacing rotted-out culverts under the Ormond shopping center is about 35% done, with businesses staying open during construction and full closeout expected in mid-2027.

At a glance

Total mentions
2
Last 30 days
1

Discussed at 1 meeting in the last 60 days; most recently Oct 26, 2026.