A $1.42 million contract with GIS Engineering will refine and permit the Engineers Canal Pump Station, with bidding targeted for spring 2027. Norco residents have waited years for this drainage relief.

At a glance

Total mentions
3
Last 30 days
0

Last discussed Aug 24, 2026.

Impact analysis

💰Financial impact

$1,423,978 for design and permitting, aimed at a spring 2027 construction bid.

✅Who benefits

Norco and surrounding residents who get flood-prone streets drained faster.