The board approved the early release package letting Woodward start site clearing, surcharge dirt, test piles, erosion control, earthwork, drainage and site utilities while the building design is finalized. A building permit allowance of about $55,000 is included.
Impact summary
Site work can start now instead of waiting for the full design, shaving time off the schedule for the new Hahnville branch.
Applicant
- Name
- St. Charles Parish Library Board of Control / Woodward Design+Build (CMAR)
At a glance
- Hearings
- 1
- Public comments
- 0
- Total mentions
- 1
Last vote · SCP Library Board of Control 6:00 PM (trimmed)
Last discussed Jan 20, 2026.
Meeting timeline (1)
Related issues (1)
We'll email you when it's on an upcoming agenda, when it's voted on and when its status changes, at most once a day.
The weekly brief for St. Charles Parish
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.